While the first two new tanks our out being fabricated, I am working on the preparing for their return. One of the big problems with taking the tanks out was the process of removing the overhead to get at the bolts that held in the cribbing around the tanks. I was determined to make it easier to get at these bolts when the tanks were returned.

The solution was to cut access holds in the overhead so I could reach the bolts while the overhead was in place. This would allow me to put up the overhead ahead of time and have access to the bolts. In the picture, you can see where a hole was cut to allow me to get a wrench up into the overhead to get at the bolt and the associated nut when putting the cribbing post back.